Line 19 (Shanghai Metro)
| Line 19 | |
|---|---|
| 19 | |
| Overview | |
| Other name | M9 (planned name) |
| Native name | 上海地铁19号线 |
| Status | Under construction |
| Locale | Baoshan, Jing'an, Hongkou, Pudong, Xuhui, Minhang Shanghai |
| Termini |
|
| Connecting lines | 2 4 6 7 8 9 10 11 12 13 14 15 18 20 23 |
| Stations | 34 |
| Website | www |
| Service | |
| Type | |
| System | |
| Operator(s) | TBA |
| Depot(s) | Chengjiang Road Depot Tieshan Road Yard |
| Rolling stock | Class A 6-car trains |
| History | |
| Planned opening | 30 December 2027 |
| Technical | |
| Track length | 46.2 km (28.7 mi) |
| Number of tracks | 2 |
| Character | Underground and elevated |
| Track gauge | 1,435 mm (4 ft 8+1⁄2 in) |
| Electrification | Overhead lines (1500 volts) |
| Operating speed | 80 km/h (50 mph) |
Line 19 is an under construction subway line on the Shanghai Metro. Its termini are planned to be Baoshan Railway Station and Hongjian Road. It is planned to be 46.2 km (28.7 mi) in length, with 34 stations. The line hopes to ease car congestion along Pudong South Road, as well as reduce crowding on the southern part of line 8, and the northern sections of lines 1 and 3.
The line was announced by the Municipal government in 2016 and is planned to finish construction and open between Baoshan Railway Station and Yierba Jinian Road on 30 December 2027.[1] The south section between Hongjian Road and Houtan is planned to finish construction in 2029, and the middle section between Houtan and Yierba Jinian Road in 2031.[2][3][4]
History
[edit]| Shanghai metro line 19 opening history | ||||||
|---|---|---|---|---|---|---|
| Segment | Commenced | Opened | Length | Station(s) | Name | Investment |
| Baoshan Railway Station - Yierba Jinian Road | 3 Mar 2024 | exp 30 December 2027[1] | 9.2 km (5.7 mi) | 8 | North section | 93.889 billion yuan |
| Houtan - Hongjian Road | 2029 | 37 km (23.0 mi) | 9 | South section | ||
| Houtan - Yierba Jinian Road | 2031 | 17 | Middle section | |||
Stations
[edit]Service routes
[edit]References
[edit]- ^ a b c 建设工程公开招标信息表 (2025-08-28). "上海市轨道交通19号线工程(北段)站台门设备采购项目" [Platform door equipment procurement project for Shanghai Metro Line 19 Project (North Section)]. Shanghai Construction Project Transaction Service Center (in Simplified Chinese). Archived from the original on 2025-08-28. Retrieved 2025-08-31.
上海市轨道交通19号线工程北段:拟建设范围虹湾路站(不含)~宝山站站(含铁山路停车场),8座车站、1座停车场,计划开通时间2027年底。供货范围: 上海市轨道交通19号线工程北段涉及8座车站,站台门共计16侧。2026年9月30日开始供货,19号线工程北段2027年12月30日进入初期运营,最终以招标人通知为准。
[The North Section of Shanghai Metro Line 19: The planned construction area is from Hongwan Road Station (excluding) to Baoshan Station (including the Tieshan Road parking lot), comprising eight stations and one parking lot. The project is scheduled to open by the end of 2027. Scope of supply: The North Section of Shanghai Metro Line 19 involves eight stations with 16 platform doors. Supply will begin on 30 September 2026, and the North Section of Line 19 will enter initial operations on 30 December 2027. Final details will be subject to the tenderee's notification.] - ^ "Shanghai Municipal Government: City mulls plan for nine more Metro projects". publicnow.com. 20 April 2016. Archived from the original on 2016-05-05. Retrieved 24 April 2016.
- ^ 上海市轨道交通19号线工程 环境影响报告书公众意见征求的网络公示 [Public Notice of Public Opinion Solicitation for the Environmental Impact Report of Shanghai Metro Line 19 Project] (in Simplified Chinese). Shanghai Municipal Government. 2023-10-09. Retrieved 2023-10-10.
- ^ "上海市轨道交通12号线西延伸、15号线南延伸、21号线一期、21号线一期东延伸、23号线一期、市域线崇明线、19号线工程电力监控系统项目招标公告" [Tender Announcement for the Power Monitoring System Project for Shanghai Metro Line 12 West Extension, Line 15 South Extension, Line 21 Phase 1, Line 21 Phase 1 East Extension, Line 23 Phase 1, Urban Rail Chongming Line, and Line 19]. Shanghai Construction Project Transaction Service Center (in Simplified Chinese). 2025-06-03. Archived from the original on 2025-06-03. Retrieved 2025-08-31.
19号线工程现阶段分段建设方案如下:1)北段:拟开通范围虹湾路站~宝山站站(含铁山停车场),9座车站1座停车场,拟开通时间2027年(或2028年);2)南段:拟开通范围虹建路站~后滩站(含澄江路车辆段),9座车站1座中间风井1座车辆段,拟开通时间2028年(或2029年);3)剩余中段:拟开通范围车站北路站~世博大道站,16站1中间风井,拟开通时间2031年(或2032年);4)全线开通时间拟2031年(或2032年);5)由于分段建设方案尚未稳定,各段具体实施范围以后续稳定方案为准。
[The current segmented construction plan for Line 19 is as follows: 1) Northern Section: The planned opening range is from Hongwan Road Station to Baoshan Station (including Tieshan Parking Lot), with 9 stations and 1 parking lot, and the planned opening time is 2027 (or 2028); 2) Southern Section: The planned opening range is from Hongjian Road Station to Houtan Station (including Chengjiang Road Depot), with 9 stations, 1 intermediate ventilation shaft and 1 depot, and the planned opening time is 2028 (or 2029); 3) The remaining middle section: The planned opening range is from Zhanbei Road Station to Shibo Avenue Station, with 16 stations and 1 intermediate ventilation shaft, and the planned opening time is 2031 (or 2032); 4) The full line is planned to be opened in 2031 (or 2032); 5) As the segmented construction plan has not yet been stabilized, the specific implementation scope of each section shall be subject to the subsequent stable plan.] - ^ "上海市轨道交通19号线工程(虹建路站—宝山站站)选线专项规划(草案公示)". 2023-04-27.